- Berkeley Lab’s 2026 edition records about 8,200 active projects in interconnection queues at the end of 2025.
- Those requests represented 1,312 gigawatts of generation and about 749 gigawatts of storage capacity.
- For completed projects with available data, the median time from request to commercial operation exceeded five years in 2025.
A queue is not a power plant
An energy proposal does not power a home. It first needs a route onto the electricity network, and Berkeley Lab’s Queued Up: 2026 Edition shows the scale of that unfinished business. At the end of 2025, roughly 8,200 active projects were seeking interconnection, representing 1,312 gigawatts of generation and about 749 gigawatts of storage.
The generation total included 773 gigawatts of solar, 220 gigawatts of wind and 253 gigawatts of natural gas. These are requests, not a construction schedule. Calling the whole queue either a clean-energy victory or a guaranteed future supply would exaggerate what it tells us.
The wait is part of the story
For projects completed in 2025, the median interval between an interconnection request and commercial operation exceeded five years in regions with available data. The same report finds that only 13% of capacity requesting connection during 2000–2020 had reached operation by the end of 2025.
Those two measures describe different groups. The first covers completed projects; the second follows an older set of requests. Neither means that every project entering today will wait exactly five years, or that every withdrawn proposal would otherwise have become a viable plant. They do establish why proposed capacity deserves a more searching headline than ‘power on the way.’
Big demand requires careful comparisons
Data centers add another planning question. A June 2026 Department of Energy report estimates their 2024 electricity use at 192 terawatt-hours, or 4.7% of U.S. consumption. Its 2030 reference case is a projection, with a substantial uncertainty range; it is not a settled bill for the future.
The report excludes cryptocurrency mining, and data centers are not synonymous with AI. Nor can annual consumption in terawatt-hours simply be set against a queue’s gigawatts of capacity. These units answer different questions, and these sources alone do not establish that data centers caused a particular household’s rate increase.
What the public should demand
Our view is that faster clean-energy delivery belongs alongside public accountability. Regulators and network planners should make connection milestones, upgrade requirements and the allocation of costs legible to the people who rely on the grid.
A useful local follow-up would trace a specific project from application through studies, financing and operation. That would test which obstacle actually matters, rather than treating every delay as proof of the same preferred explanation. The climate needs completed projects; the public deserves a clear account of their price and benefit.
Build the clean-energy network faster, with transparent costs and public oversight. A long list of proposals is not the climate outcome.
Where we standSources & the record.
Checked Nov 27, 2026Follow the evidence for yourself. Source dates and the periods covered matter; an official statement is attributed, not treated as independent proof.
- Queued Up: 2026 Edition Lawrence Berkeley National Laboratory 2026-06
Requests through December 31, 2025. Publication record says May 2026; project page dates report publication to June. Queue entries are proposals, not committed construction, and exclude load-connection queues.
- United States Data Center Energy Usage Report: 2025 Update U.S. Department of Energy / Berkeley Lab 2026-06-18
2024 is the last historical year; later values are modeled projections. National consumption estimates exclude cryptocurrency mining. Not all data-center electricity is used for AI.
0 comments
In conversation order